GuidesChangelog
Guides
Guides
Guides

Transmission Network Use of System (TNUoS)

TNUoS charges depend on the grid connection, asset size, and duration.

The TNUoS charging regime is slightly complicated for batteries. It depends on if the site is transmission- or distribution-connected, where it is, and what it does during Triad periods.

Generally, if you import during a Triad, you'll pay.

If you export during a Triad, you might get some revenue depending on where the site is, according to Embedded Export tariffs.

If the site is larger than 100MW or connected directly to the transmission network, you also face a fixed cost Wider Generation tariffs.

For reference, all costs (or revenues) we display in our forecast numbers are purely for the battery on a site. Batteries on co-located sites will be subject to different TNUoS revenues.

TNUoS Overview

Grid connectionImport (demand)Export (generation)
DistributionFixed cost: £0 for batteries due to final demand exemption

Flexible (Triad) cost: £ avoidable, (and smaller than it used to be) as per network rates
Fixed cost: £0

Flexible (Triad) cost: £ avoidable, as per Embedded Export rates. £0 for Scotland, Northern, North West & Yorkshire
Transmission or
embedded > 100MW assets
Fixed cost: see export

Flexible (Triad) cost: £ avoidable, (and smaller than it used to be) as per network rates
Fixed cost: £+/- set by Wider Generation tariffs, and annual load factor (ALF) calculation

Flexible (Triad) cost: £0

Batteries connected to the distribution network are exempt from TNUoS fixed import fees (provided they submit a Non-Final Demand form to NGESO).

All batteries (distribution or transmission) are exposed to flexible TNUoS charges if they import during a Triad, according to import rates (Figure 2 here). Distribution-connected assets get paid flexible TNUoS rates depending on where they are and their average power over Triad periods, according to Embedded Export Tariffs (shown below).

Transmission-connected assets are subject to fixed-cost TNUoS charges as per the Wider Generation tariffs. They can be positive or negative. Annual load factors are used in the calculation of these charges. For batteries without three years of historical data, the generic Annual Load Factor (ALF) is 1.2391% (source).





Transmission-connected batteries pay fixed TNUoS

Export rates for transmission-connected generation have shifted from time-of-use (via the Triad mechanism) to a fixed rate via the Wider Generation tariffs. This is a result of the Targeted Charging Review.

The rate can be positive or negative and varies throughout the country. See Figure 4 here.

For example, let's model a transmission-connected battery site in South Wales, due to come online during 2025

Transmission-connected batteries fall into the 'Convention Carbon' generating class for TNUoS calculations.

The calculation for the Wider TNUoS tariff, Conventional Carbon, is:

Taking numbers from the 5-year view of TNUoS tariffs, in the year 2025/2026 (p.14) and assuming the site has no historical data, we use an Annual Load Factor (ALF) generic for storage of 1.2391% (p.71).

This gives the calculation:

2.349244 + (- 8.341082 x 1.2391%) + (0 x 1.2391%)+ - 2.167565 £/kW = 0.078325 £/kW (to 5 significant figures), or £78.33/MW/year.

The site will be charged £78.33/MW over 2025 in TNUoS fees, plus the variable rate for anything it imports during triad periods (which would hopefully be negligible).

Our forecast for 2025 shows a site in South Wales earning ~£85k/MW in 2025. The TNUoS fee, therefore, constitutes a cost equivalent to 0.1% of annual revenues.

Note: Fixed TNUoS fees are charged in £/kW, and the kW rating is as the site is listed in the TEC register. The maximum capacity is taken if the site size listed in the TEC register changes during the year.

How does this look in Scotland?

In North Scotland (the most expensive of the Scottish demand regions), the calculation looks like:

2.747082 + (27.563546 x 1.2391%) + (5.142500 x 1.2391%) - 1.296387 = 3.13938 £/kW or £3,139/MW/year.

In 2025, our forecast shows this equates to around 5% of the site revenues - so more significant.

The Modo Forecast revenues do not include fixed network fees

In the same way we do not include fixed charges like standing charges, FIT or RO line items on the electricity bill, we don't include fixed TNUoS rates in the forecast line items, like Wider Generation tariffs. These should be considered in the OPEX costs of the site.